"Providing Hometown Reliability"
Updated 11/29/23
The conduit contractor is finished with the first 2 contracts except a handful of short sections. He has started on some of the creek bores for the third contract. MMU crews are mostly complete with a section of conduit on 160th Road. There is one creek crossing on YY that will delay that area until we can overcome the rockiness. MMU crews have finished pulling in fiber for the EE area and the 230th area. Splicing is mostly complete in those areas.
Backbone construction is complete for Grant 1. Come in and sign up anytime.
All Areas | complete | stop by to sign up |
NOTE: The maps in the table below show planned areas in Grant 2. However, the contracts for conduit do not necessarily match the entire area for any given year. For example, the Kittyhawk map shows the entire Kittyhawk to Quarry area, but only blue the lines on the map are planned for 2023. The completion percentages in the table only reflect the part of the areas that are planned this year. There may be some additional conduit installed by MMU personnel which could increase what gets done this year. Bold lines on maps are the areas of construction.
Contract 2201 (South) | Complete except an area where crops were on the state right-of-way and a couple of creek crossing | ||||
Kittyhawk | 2023 portion complete | Map | |||
165th Rd | 2023 portion complete | Map | |||
Mt Olive | Complete | Map | |||
YY South | contract conduit 95% complete | Map | |||
185th | conduit 99% complete | Map | |||
EE South | contract conduit complete | fiber complete | splicing complete | Map | |
200th | conduit 99% complete | Map | |||
Contract 2202 (West) | Conduit 99% complete | ||||
Daybreak | conduit complete | fiber soon | Map | ||
230th | conduit complete | fiber complete | splicing 50% complete | Map | |
250th | conduit complete | fiber 20% complete | splicing 10% complete | Map | |
Golden North | conduit 99% complete | Map | |||
Contract 2203 (North) | conduit 5% complete | ||||
Remaining Round 2 | Bids for another 110 miles are due early December. The rockier areas will be bid seperately. |